COMPLETED PROJECTS
SHUQAIQ DESALINATION PLANT
- Project No : SDP025
- Client : SWCC / Rawafid Industry
- Location : Shuqaiq / Saudi Arabia
- Project Start : Dec 2019
- Duration : 12 Months
- Manpower : 250 People
- Value : 15,030,859.00 $
Turnkey civil and architectural works for the Shuqaiq Satellite Desalination Plant Project.
Works included Sea Water Intake & Outfall, Pretreatment Area & Wastewater Area, RO Building, Electrical and Control Building, Post Treatment Area and Chemical Storage Building.
Scope included 56,531 m3 excavation, 92,370 m3 filling and 12,932 m³ concrete work.

SHOAIBA DESALINATION PLANT

DUBA DESALINATION PLANT

KAEC DESALINATION PLANT

YANBU POWER and DESALINATION PLANT

PETRO RABIGH CLEAN FUEL and SULPHUR RECOVERY UNIT

PETRORABIGH II NON-PROCESS BDG.S CONSTRUCTION PROJECT

PETRORABIGH II BLAST PROOF MANUFACTURING BDG.S PROJECT

RABIGH II REFINING AND PETROCHEMICAL PROJECT

BAHRI FLOATING DESALINATION PLANT

SHUQAIQ DESALINATION PLANT

DAMMAM ARAMCO HOUSING PROJECT

PETRORABIGH II INITIAL START-UP TEAM ACCOMODATION PROJECT

KING KHALID UNIVERSITY CONFERENCE HALL BUILDING

KING KHALID UNIVERSITY GENERAL ADMINISTRATION BUILDING