COMPLETED PROJECTS
BAHRI FLOATING DESALINATION PLANT
- Project No : SFD027
- Client : SWCC / Metito Saudi Limited
- Location : Shuqaiq / Saudi Arabia
- Project Start : July 2020
- Duration : 14 Months
- Manpower : 120 People
- Value : 2,801,220.00 $
Turnkey civil works for the Bahri Floating Desalination Plant Project.
Project works included of Chemical Building, Chemical Wastewater Collection Sump, Carbon Dioxide Storage Tank and Electrical Building
Scope included of 37,000 m³ excavation, 1,060 m³ concrete and 137,8 ton reinforcing bar works.

SHOAIBA DESALINATION PLANT

DUBA DESALINATION PLANT

KAEC DESALINATION PLANT

YANBU POWER and DESALINATION PLANT

PETRO RABIGH CLEAN FUEL and SULPHUR RECOVERY UNIT

PETRORABIGH II NON-PROCESS BDG.S CONSTRUCTION PROJECT

PETRORABIGH II BLAST PROOF MANUFACTURING BDG.S PROJECT

RABIGH II REFINING AND PETROCHEMICAL PROJECT

BAHRI FLOATING DESALINATION PLANT

SHUQAIQ DESALINATION PLANT

DAMMAM ARAMCO HOUSING PROJECT

PETRORABIGH II INITIAL START-UP TEAM ACCOMODATION PROJECT

KING KHALID UNIVERSITY CONFERENCE HALL BUILDING

KING KHALID UNIVERSITY GENERAL ADMINISTRATION BUILDING